Today marks exactly 1 week until the weekend of the Banner Production hardware migration! As mentioned in previous BCM meetings, the Dev and Test environments are fully operational and all testing should be in process or completed.
Here is the tentative schedule of events leading to the upcoming Banner hardware changeover for PBAN on September 11, 2021. This lists dates for data change request freezes and the event chain for the changeover.
DATE EVENT START & END TIMES
August 30, 2021 – ODS Changes Freeze
September 7, 2021 – Banner Changes Freeze
September 10, 2021 – Banner DB Cutover 5:00 PM 6:00 AM
September 10, 2021 – ODS DB Cutover 5:00 PM 6:00 AM
September 10, 2021 – Job Sub Server Cutover 5:00 PM 6:00 AM
September 10, 2021 – GoldenGate Deployment 5:00 PM 6:00 AM
September 10, 2021 – DataGuard DB Deployment 5:00 PM 6:00 AM
September 11, 2021 – 3rd Party Software Config 7:00 AM 1:00 PM
September 11, 2021 – 3rd Party Software Checkout 7:00 AM 8:00 PM
September 11, 2021 – No Fallback 7:00 AM
September 12, 2021 – System Checkout 7:00 AM noon
September 14, 2021 – Banner/ODS Changes Unfreeze